When it is allowed

The last resort

Using a crane to hoist employees is prohibited except where the employer demonstrates that conventional means of reaching the work area (a personnel hoist, ladder, stairway, aerial lift, elevating work platform or scaffold) would be more hazardous, or are not possible because of the structural design or worksite conditions. This does not apply to steel erection work under subpart R or routine access to underground worksites by shaft.

Reference: 29 CFR 1926.1431(a) · 29 CFR 1926.1431(b)(1) · 29 CFR 1926.1431(n) · 29 CFR 1926.1431(m) · 29 CFR 1926.1431(b)(2) · 29 CFR 1926.1431(b)(2)(i) · 29 CFR 1926.1431(b)(2)(ii) · 29 CFR 1926.1431(b)(2)(iii) · 29 CFR 1926.1431(b)(2)(iv) · 29 CFR 1926.1431(m)(2) · 29 CFR 1926.1431(m)(3)

Set-up, capacity and devices

Level, firm and half capacity

Reference: 29 CFR 1926.1431(c)(1) · 29 CFR 1926.1431(c)(2) · 29 CFR 1926.1431(d)(1) · 29 CFR 1926.1431(d)(4) · 29 CFR 1926.1431(d)(5)(vi) · 29 CFR 1926.1431(d)(5)(vii) · 29 CFR 1926.1431(d)(6) · 29 CFR 1926.1431(d)(5)(i) · 29 CFR 1926.1431(d)(5)(i)(A) · 29 CFR 1926.1431(d)(5)(i)(B) · 29 CFR 1926.1431(d)(5)(ii) · 29 CFR 1926.1431(d)(5)(iii) · 29 CFR 1926.1431(d)(5)(iii)(A) · 29 CFR 1926.1431(d)(5)(iii)(B) · 29 CFR 1926.1431(d)(5)(iv) · 29 CFR 1926.1431(d)(5)(v)

The platform and its rigging

Platform, loading and rigging

Reference: 29 CFR 1926.1431(e) · 29 CFR 1926.1431(f) · 29 CFR 1926.1431(g) · 29 CFR 1926.1431(e)(6) · 29 CFR 1926.1431(e)(7) · 29 CFR 1926.1431(e)(9) · 29 CFR 1926.1431(e)(11) · 29 CFR 1926.1431(f)(1)

Trial lift and proof test

Test before people ride

Trial lift. With the platform unoccupied and loaded at least to the anticipated lift weight, lift from where employees will enter to each location where the platform will be positioned. Do it immediately prior to each shift in which personnel will be hoisted, and again when the equipment is moved and set up in a new or previously used location, or the lift route changes (unless the competent person determines the new route presents no new safety factors). The competent person then inspects for any defect or adverse effect and confirms the test weight is removed.

Right before each lift, the platform is hoisted a few inches with the people and materials on board and inspected by a competent person for security and balance.

Proof test. At each jobsite before hoisting employees, and after any repair or modification, the platform and rigging are proof tested to 125 percent of the platform's rated capacity, held suspended for at least five minutes. No personnel hoisting until the competent person determines the test was passed.

Reference: 29 CFR 1926.1431(h) · 29 CFR 1926.1431(j) · 29 CFR 1926.1431(h)(2)(ii) · 29 CFR 1926.1431(h)(4)(i) · 29 CFR 1926.1431(h)(4)(ii)

In the platform

Work practices

Reference: 29 CFR 1926.1431(k) · 29 CFR 1926.1431(k)(2)(i) · 29 CFR 1926.1431(k)(2)(iii) · 29 CFR 1926.1431(k)(10)(i)

Need proof of training? The full course (20 min) adds practice questions, a job scenario, the final quiz and a certificate your employer can verify.

Take the course

Sources

Fact-checked against the regulation text on October 09, 2026. This certificate records completion of awareness training based on OSHA 29 CFR 1926.1431. It is not an OSHA card or license, it is not crane operator certification or qualification, and it does not make anyone a competent person or qualified person. Section 1926.1431 has no training requirement of its own; its requirements are supplemental to the other requirements of Subpart CC, which still apply. Before hoisting personnel, your employer must still hold the pre-lift meeting required by 29 CFR 1926.1431(m) to review the applicable requirements of the section and the procedures that will be followed, attended by the equipment operator, signal person (if used for the lift), employees to be hoisted, and the person responsible for the task to be performed, held prior to the trial lift at each new work location and repeated for any employees newly assigned to the operation.

This guide explains the rule in plain words. Always read the regulation itself and your employer's site-specific procedures.