Home / Standards guides / Demolition Safety
Black Belt Safety · Free guide

Demolition Safety

For demolition workers and the supervisors who run their crews: confirm the job is ready to start, control openings, chutes and debris drops, keep the structure stable as it comes down, and stay clear of mechanical demolition hazards.

Based on OSHA 29 CFR 1926 Subpart T, Demolition (1926.850, 1926.851, 1926.852, 1926.853, 1926.854, 1926.856, 1926.857 and 1926.859) · about 7 min read

Need proof of training? The full course (20 min) adds practice questions, a job scenario, the final quiz and a certificate your employer can verify.

Take the course
Before demolition starts

The engineering survey and damaged structures

No one starts until the survey is done

Before employees are allowed to start demolition, a competent person must make an engineering survey of the structure. It checks the condition of the framing, floors and walls, and the possibility of unplanned collapse of any part of it.

Damaged buildings

When employees are required to work inside a structure damaged by fire, flood, explosion or other cause, the walls or floor must be shored or braced.

Supervisors: ask to see the written survey before you send your crew in.

Reference: 29 CFR 1926.850(a) · 29 CFR 1926.850(b)

Before demolition starts

Utilities and hidden hazards

Service lines

Before demolition work starts, all electric, gas, water, steam, sewer and other service lines must be shut off, capped, or otherwise controlled, outside the building line. Any utility company involved must be notified in advance.

If power, water or other utilities must stay on during demolition, those lines must be temporarily relocated as necessary and protected.

What was in the pipes and tanks?

It must be determined whether hazardous chemicals, gases, explosives, flammable materials or similar dangerous substances were used in any pipes, tanks or other equipment on the property. When they are apparent or suspected, testing and purging must be done and the hazard eliminated before demolition is started.

Glass

Where a hazard exists from fragmenting glass, that hazard must be removed.

Reference: 29 CFR 1926.850(c) · 29 CFR 1926.850(d) · 29 CFR 1926.850(e) · 29 CFR 1926.850(f)

Access, openings and debris drops

Getting in, and holes in walls and floors

Access

Wall openings

Where you could fall through a wall opening, it must be protected to a height of approximately 42 inches.

Dropping debris through floor holes without a chute

Other floor openings

Reference: 29 CFR 1926.850(k) · 29 CFR 1926.851(a) · 29 CFR 1926.850(g) · 29 CFR 1926.850(h) · 29 CFR 1926.850(i) · 29 CFR 1926.854(e)

Access, openings and debris drops

Parts of a safe debris chute

Material may not be dropped outside the exterior walls of the structure unless that area is effectively protected. A chute is the usual way.

Guardrail
Any chute opening where workers dump debris needs a substantial guardrail approximately 42 inches above the surface they stand on.
Toeboard or bumper
Where material is dumped from mechanical equipment or wheelbarrows, each chute opening needs a securely attached toeboard or bumper not less than 4 inches thick and 6 inches high.
Openings and closures
A chute at more than 45° from horizontal is entirely enclosed except for openings with closures at or about floor level. Openings are no more than 48 inches high along the chute wall, and below the top floor they stay closed when not in use.
Discharge gate
Each chute has a substantial gate at or near the discharge end. A competent employee is assigned to control the gate and the backing and loading of trucks.
Discharge area
When operations are not in progress, the area around the discharge end must be securely closed off.

Reference: 29 CFR 1926.852(a) · 29 CFR 1926.852(b) · 29 CFR 1926.852(c) · 29 CFR 1926.852(d) · 29 CFR 1926.852(e) · 29 CFR 1926.852(f)

Keeping the structure stable

Top down, one story at a time

Work from the top down

Exterior walls and floors come down starting at the top and moving downward. Each story is removed and dropped into the storage space before removal starts on the story below. The exception is preparatory work, such as cutting holes for chutes or drops and preparing storage space.

Leave the supports alone

Structural or load-supporting members on a floor are not cut or removed until all stories above have been demolished and removed. Cutting floor beams to dispose of materials or install equipment is still allowed when the rules for floor openings and manual floor removal are met.

Walls

Reference: 29 CFR 1926.850(j) · 29 CFR 1926.854(d) · 29 CFR 1926.854(b) · 29 CFR 1926.854(c) · 29 CFR 1926.854(a)

Keeping the structure stable

Floors, storage and equipment loads

Reference: 29 CFR 1926.853 · 29 CFR 1926.857(a) · 29 CFR 1926.856(a) · 29 CFR 1926.856(b)

Mechanical demolition and ongoing inspection

Balling, clamming and pulling walls

Stay out of the zone

When balling or clamming is being done, no workers are allowed in any area that can be adversely affected. At other times, only the workers needed for the operation are allowed in that area.

The demolition ball

Pulling walls over

Reference: 29 CFR 1926.859(a) · 29 CFR 1926.859(b) · 29 CFR 1926.859(c) · 29 CFR 1926.859(d) · 29 CFR 1926.859(e) · 29 CFR 1926.859(f)

Mechanical demolition and ongoing inspection

Inspections continue as the work goes on

The first survey is not the last look. During demolition, a competent person makes continuing inspections as the work progresses, looking for hazards from weakened or deteriorated floors or walls, or loosened material.

When a hazard is found: no employee may work there until it is corrected by shoring, bracing or other effective means.

Workers: if a floor sags, a wall cracks or material is hanging loose, stop and tell the competent person.

Reference: 29 CFR 1926.859(g)

Need proof of training? The full course (20 min) adds practice questions, a job scenario, the final quiz and a certificate your employer can verify.

Take the course

Sources

Fact-checked against the regulation text on October 09, 2026. This certificate records completion of awareness training based on OSHA 29 CFR 1926.850, 1926.851, 1926.852, 1926.853, 1926.854, 1926.856, 1926.857 and 1926.859. It is not an OSHA card or license, and it does not make anyone a competent person. Subpart T has no training paragraph of its own, and this certificate does not by itself meet the general training requirement of 29 CFR 1926.21(b)(2). Your employer must still instruct you in the recognition and avoidance of unsafe conditions and the regulations applicable to your work environment to control or eliminate any hazards.

This guide explains the rule in plain words. Always read the regulation itself and your employer's site-specific procedures.