For the ironworker on a steel erection crew: know the fall protection heights for general work, connecting and controlled decking zones, stay out from under suspended loads, do not release a beam from the hoisting line before it is bolted, and keep openings and loose items from becoming the next accident.
Need proof of training? The full course (20 min) adds practice questions, a job scenario, the final quiz and a certificate your employer can verify.
Take the courseAt heights over 15 and up to 30 feet, a connector must be provided with a personal fall arrest, positioning device or fall restraint system and wear the equipment needed to be able to tie off, or be provided other fall protection.
On multi-story structures, perimeter safety cables are installed at the final interior and exterior floor perimeters as soon as the metal decking is installed.
Reference: 29 CFR 1926.760(a)(1) · 29 CFR 1926.760(a)(3) · 29 CFR 1926.760(b)(1) · 29 CFR 1926.760(b)(2) · 29 CFR 1926.760(b)(3) · 29 CFR 1926.760(a)(2)
A CDZ may be set up over 15 and up to 30 feet above a lower level, where metal decking is first being installed and forms the leading edge.
Reference: 29 CFR 1926.760(c) · 29 CFR 1926.760(c)(1) · 29 CFR 1926.760(c)(2) · 29 CFR 1926.760(c)(3) · 29 CFR 1926.760(c)(4) · 29 CFR 1926.760(c)(5) · 29 CFR 1926.760(c)(6) · 29 CFR 1926.760(c)(7)
Routes for suspended loads must be pre-planned so that no employee is required to work directly below a suspended load, except:
Do not ride the headache ball, hook or load. It may not be used to transport personnel, except on a personnel platform meeting the crane rules. The crane operator has the authority to stop and refuse to handle loads whenever there is any doubt as to safety.
Reference: 29 CFR 1926.753(d)(1) · 29 CFR 1926.753(d)(2) · 29 CFR 1926.753(c)(3) · 29 CFR 1926.753(c)(1)(iv) · 29 CFR 1926.753(c)(4)
Structural stability must be maintained at all times during erection. For you as a connector, a key part of that is the bolts.
For cantilevered members, a competent person decides whether more than two bolts are needed. If they are, they must be installed.
Reference: 29 CFR 1926.756(a)(1) · 29 CFR 1926.756(a)(2) · 29 CFR 1926.756(b) · 29 CFR 1926.754(a)
Outside a CDZ, lay metal decking tightly and secure it immediately on placement. At the end of the shift, or when conditions require, secure decking against displacement.
All materials, equipment and tools not in use while aloft must be secured against accidental displacement. The controlling contractor must bar other work below steel erection unless overhead protection is provided for the employees below.
Reference: 29 CFR 1926.754(e)(2)(iii) · 29 CFR 1926.754(e)(3)(i) · 29 CFR 1926.754(e)(3)(ii) · 29 CFR 1926.754(e)(3)(iii) · 29 CFR 1926.754(e)(3)(iv) · 29 CFR 1926.754(e)(5)(i) · 29 CFR 1926.754(e)(1)(v) · 29 CFR 1926.759(a) · 29 CFR 1926.759(b)
Need proof of training? The full course (20 min) adds practice questions, a job scenario, the final quiz and a certificate your employer can verify.
Take the courseFact-checked against the regulation text on October 09, 2026. This certificate records completion of awareness training based on OSHA 29 CFR 1926.753, 1926.754, 1926.756, 1926.759 and 1926.760. It is not an OSHA card or license, and it does not by itself meet the training requirements of 29 CFR 1926.761. Your employer must still train each employee exposed to a fall hazard under a training program covering the areas listed in 1926.761(b), provide the special training in 1926.761(c) to each connector, to each employee working in a controlled decking zone, and to each employee who performs multiple lift rigging, and have this training provided by a qualified person.
This guide explains the rule in plain words. Always read the regulation itself and your employer's site-specific procedures.