1926.652(g)(2): Digging Below a Trench Shield

By Black Belt Safety Editorial Team Official text as of octubre 15, 2026 Data updated octubre 20, 2026 3 min read

In plain words:

Employers may dig earth material to a level not greater than 2 feet (.61 m) below the bottom of a trench shield, but only if the shield is designed for the forces of the full trench depth and there are no signs, while the trench is open, of possible soil loss from behind or below the shield bottom.

Key takeaways

  • 1926.652(g)(2) is part of OSHA's construction standards (29 CFR Part 1926, Subpart P).
  • OSHA cited it 38 times in the last 3 years, in 38 inspections, with $158,151 in current penalties.
  • Most citations: IL (8), OK (5), MD (4).
  • Related part: 1926.652(g) Shield systems (137 citations).
  • Free 5-minute toolbox talk for your crew below.
38citations, 3 years
$158,151current penalties
38inspections
0linked injury cases
In this article
  1. What this rule covers
  2. Official text
  3. Where and how often it was cited
  4. Free toolbox talk
  5. OSHA interpretation letters
  6. Related parts of this rule
  7. Get your crew competent
  8. Frequently asked questions
  9. About this page

What this rule covers

29 CFR 1926.652(g)(2) ("Additional requirement for shield systems used in trench excavations") is one requirement inside 1926.652 Requirements for protective systems, an OSHA construction standard (Part 1926, Subpart P). The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

(2) Additional requirement for shield systems used in trench excavations. Excavations of earth material to a level not greater than 2 feet (.61 m) below the bottom of a shield shall be permitted, but only if the shield is designed to resist the forces calculated for the full depth of the trench, and there are no indications while the trench is open of a possible loss of soil from behind or below the bottom of the shield. 38 citations

Source: eCFR, text current as of 2026-10-15. Read all of 1926.652.

Where and how often it was cited

YearCitations
20232
202414
202510
202612

Top states: IL (8), OK (5), MD (4), CO (3), MA (2)

Largest penalties

EmployerLocationPenalty for this rule
BLUE STAR UTILITIES, LLCANNA, TX$24,842
REVOLI CONSTRUCTION CO., INCSOUTH YARMOUTH, MA$16,550
ELDER CORPORATIONWAUKEE, IA$14,063
RFX2026XJW184X0193 - MCCAIN CONSTRUCTION LLCSURPRISE, AZ$11,823
H&H PLUMBING AND UTILITIES, INC.OKLAHOMA CITY, OK$10,000

Free toolbox talk

A 5-minute crew talk on 1926.652(g)(2), plus alerts when this rule changes. Free.




OSHA interpretation letters

Related parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey, Dana Reyes

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

How far below a trench shield can we dig?

To a level not greater than 2 feet (.61 m) below the bottom of the shield.

What design is needed to dig below the shield?

The shield must be designed to resist the forces calculated for the full depth of the trench.

When must we stop digging below the shield?

If there are indications while the trench is open of a possible loss of soil from behind or below the bottom of the shield.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.

Desplácese hacia arriba