29 CFR 1910 · General Industry · Subpart N

1910.179(b)(5): Crane Rated Load Marking

By Black Belt Safety Editorial Team Official text as of octubre 15, 2026 Data updated octubre 22, 2026 3 min read

In plain words:

Employers must mark the rated load of an overhead or gantry crane plainly on each side of the crane. If the crane has more than one hoisting unit, each hoist must have its rated load marked on it or its load block, clearly legible from the ground or floor.

Key takeaways

  • 1910.179(b)(5) is part of OSHA's general industry standards (29 CFR Part 1910, Subpart N).
  • OSHA cited it 32 times in the last 3 years, in 32 inspections, with $104,539 in current penalties.
  • Most citations: NJ (8), TX (3), OH (2).
  • Related part: 1910.179(b) General requirements (57 citations).
  • Free 5-minute toolbox talk for your crew below.
32citations, 3 years
$104,539current penalties
32inspections
0linked injury cases
In this article
  1. What this rule covers
  2. Official text
  3. Where and how often it was cited
  4. Free toolbox talk
  5. OSHA interpretation letters
  6. Related parts of this rule
  7. Get your crew competent
  8. Frequently asked questions
  9. About this page

What this rule covers

29 CFR 1910.179(b)(5) ("Rated load marking") is one requirement inside 1910.179 Overhead and gantry cranes, an OSHA general industry standard (Part 1910, Subpart N). The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

(5) Rated load marking. The rated load of the crane shall be plainly marked on each side of the crane, and if the crane has more than one hoisting unit, each hoist shall have its rated load marked on it or its load block and this marking shall be clearly legible from the ground or floor. 32 citations

Source: eCFR, text current as of 2026-10-15. Read all of 1910.179.

Where and how often it was cited

YearCitations
20231
202413
202510
20268

Top states: NJ (8), TX (3), OH (2), MD (2), CO (2)

Largest penalties

EmployerLocationPenalty for this rule
ALAMO STRUCTURAL STEEL, LLCVICTORIA, TX$14,895
MODERN MACHINE SHOP, INC.LAREDO, TX$9,847
SCHUFF STEEL COMPANYLYNCHBURG, VA$7,865
GUERDON, LLCBOISE, ID$7,449
SPRUCE RUN RECREATION AREACLINTON, NJ$7,000

Free toolbox talk

A 5-minute crew talk on 1910.179(b)(5), plus alerts when this rule changes. Free.




OSHA interpretation letters

Related parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey, Dana Reyes

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

Where must a crane's rated load be marked?

Plainly on each side of the crane.

What if there is more than one hoist?

Each hoist must have its rated load marked on it or its load block.

Must the marking be readable from the floor?

Yes. It must be clearly legible from the ground or floor.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.

Desplácese hacia arriba