29 CFR 1910 · General Industry · Subpart R

1910.269(m): Deenergizing Lines for Worker Protection

By Black Belt Safety Editorial Team Official text as of octubre 15, 2026 Data updated octubre 21, 2026 8 min read

In plain words:

When deenergizing transmission and distribution lines and equipment to protect employees, employers must designate one crew member in charge of the clearance and follow paragraph (m)(3) in the order specified. If no system operator is in charge, that employee performs the system operator's functions. Conductors and parts deenergized under other procedures must be treated as energized, and some steps and tags are not needed when one crew has sole, visible control of the disconnect.

Key takeaways

  • 1910.269(m) is part of OSHA's general industry standards (29 CFR Part 1910, Subpart R).
  • OSHA cited it 24 times in the last 3 years, in 21 inspections, with $165,441 in current penalties.
  • 4 deaths are linked to inspections that cited this rule.
  • Most citations: CO (3), TN (3), HI (3).
  • Related part: 1910.269(m)(3) Deenergizing lines and equipment (20 citations).
  • Free 5-minute toolbox talk for your crew below.
24citations, 3 years
$165,441current penalties
21inspections
4linked deaths
In this article
  1. What this rule covers
  2. Official text
  3. Injuries linked to this rule
  4. Where and how often it was cited
  5. Free toolbox talk
  6. OSHA interpretation letters
  7. Related parts of this rule
  8. Get your crew competent
  9. Frequently asked questions
  10. About this page

What this rule covers

29 CFR 1910.269(m) ("Deenergizing lines and equipment for employee protection") is one requirement inside 1910.269 Electric power generation, transmission, and distribution, an OSHA general industry standard (Part 1910, Subpart R). It includes 30 sub-paragraphs. The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

(m) Deenergizing lines and equipment for employee protection — 24 citations

(1) Application. Paragraph (m) of this section applies to the deenergizing of transmission and distribution lines and equipment for the purpose of protecting employees. See paragraph (d) of this section for requirements on the control of hazardous energy sources used in the generation of electric energy. Conductors and parts of electric equipment that have been deenergized under procedures other than those required by paragraph (d) or (m) of this section, as applicable, shall be treated as energized. Open (m)(1)

(2) General. Open (m)(2) 4 citations

(i) If a system operator is in charge of the lines or equipment and their means of disconnection, the employer shall designate one employee in the crew to be in charge of the clearance and shall comply with all of the requirements of paragraph (m)(3) of this section in the order specified. 1 citations

(ii) If no system operator is in charge of the lines or equipment and their means of disconnection, the employer shall designate one employee in the crew to be in charge of the clearance and to perform the functions that the system operator would otherwise perform under paragraph (m) of this section. All of the requirements of paragraph (m)(3) of this section apply, in the order specified, except as provided in paragraph (m)(2)(iii) of this section. Open (m)(2)(ii) 2 citations

(iii) If only one crew will be working on the lines or equipment and if the means of disconnection is accessible and visible to, and under the sole control of, the employee in charge of the clearance, paragraphs (m)(3)(i), (m)(3)(iii), and (m)(3)(v) of this section do not apply. Additionally, the employer does not need to use the tags required by the remaining provisions of paragraph (m)(3) of this section.

(iv) If two or more crews will be working on the same lines or equipment, then: 1 citations

(A) The crews shall coordinate their activities under paragraph (m) of this section with a single employee in charge of the clearance for all of the crews and follow the requirements of paragraph (m) of this section as if all of the employees formed a single crew, or 1 citations

(B) Each crew shall independently comply with paragraph (m) of this section and, if there is no system operator in charge of the lines or equipment, shall have separate tags and coordinate deenergizing and reenergizing the lines and equipment with the other crews.

(v) The employer shall render any disconnecting means that are accessible to individuals outside the employer's control (for example, the general public) inoperable while the disconnecting means are open for the purpose of protecting employees.

(3) Deenergizing lines and equipment. Open (m)(3) 20 citations

(i) The employee that the employer designates pursuant to paragraph (m)(2) of this section as being in charge of the clearance shall make a request of the system operator to deenergize the particular section of line or equipment. The designated employee becomes the employee in charge (as this term is used in paragraph (m)(3) of this section) and is responsible for the clearance. 2 citations

(ii) The employer shall ensure that all switches, disconnectors, jumpers, taps, and other means through which known sources of electric energy may be supplied to the particular lines and equipment to be deenergized are open. The employer shall render such means inoperable, unless its design does not so permit, and then ensure that such means are tagged to indicate that employees are at work. Open (m)(3)(ii) 7 citations

(iii) The employer shall ensure that automatically and remotely controlled switches that could cause the opened disconnecting means to close are also tagged at the points of control. The employer shall render the automatic or remote control feature inoperable, unless its design does not so permit.

(iv) The employer need not use the tags mentioned in paragraphs (m)(3)(ii) and (m)(3)(iii) of this section on a network protector for work on the primary feeder for the network protector's associated network transformer when the employer can demonstrate all of the following conditions:

(A) Every network protector is maintained so that it will immediately trip open if closed when a primary conductor is deenergized;

(B) Employees cannot manually place any network protector in a closed position without the use of tools, and any manual override position is blocked, locked, or otherwise disabled; and

(C) The employer has procedures for manually overriding any network protector that incorporate provisions for determining, before anyone places a network protector in a closed position, that: The line connected to the network protector is not deenergized for the protection of any employee working on the line; and (if the line connected to the network protector is not deenergized for the protection of any employee working on the line) the primary conductors for the network protector are energized.

(v) Tags shall prohibit operation of the disconnecting means and shall indicate that employees are at work.

(vi) After the applicable requirements in paragraphs (m)(3)(i) through (m)(3)(v) of this section have been followed and the system operator gives a clearance to the employee in charge, the employer shall ensure that the lines and equipment are deenergized by testing the lines and equipment to be worked with a device designed to detect voltage. Open (m)(3)(vi) 8 citations

(vii) The employer shall ensure the installation of protective grounds as required by paragraph (n) of this section. 2 citations

(viii) After the applicable requirements of paragraphs (m)(3)(i) through (m)(3)(vii) of this section have been followed, the lines and equipment involved may be considered deenergized. Open (m)(3)(viii)

(ix) To transfer the clearance, the employee in charge (or the employee's supervisor if the employee in charge must leave the worksite due to illness or other emergency) shall inform the system operator and employees in the crew; and the new employee in charge shall be responsible for the clearance. Open (m)(3)(ix)

(x) To release a clearance, the employee in charge shall:

(A) Notify each employee under that clearance of the pending release of the clearance;

(B) Ensure that all employees under that clearance are clear of the lines and equipment;

(C) Ensure that all protective grounds protecting employees under that clearance have been removed; and

(D) Report this information to the system operator and then release the clearance.

(xi) Only the employee in charge who requested the clearance may release the clearance, unless the employer transfers responsibility under paragraph (m)(3)(ix) of this section.

(xii) No one may remove tags without the release of the associated clearance as specified under paragraphs (m)(3)(x) and (m)(3)(xi) of this section.

(xiii) The employer shall ensure that no one initiates action to reenergize the lines or equipment at a point of disconnection until all protective grounds have been removed, all crews working on the lines or equipment release their clearances, all employees are clear of the lines and equipment, and all protective tags are removed from that point of disconnection. 1 citations

Source: eCFR, text current as of 2026-10-15. Read all of 1910.269.

Injuries linked to this rule

4 deaths are linked to inspections where OSHA cited 1910.269(m).

Employee replacing water damaged wire dies when electrocuted
2024-07-31 · Fatal · MURRAY, KY

On July 31, 2024, an employee working for an electrical contractor was shocked while replacing flood-damaged electrical cable. The employee died due to electrocution.

See all 4 cases

Full case list with employer, penalty, filters and download is part of OSHA Data (Purple Belt).

Unlock with Purple Belt

Where and how often it was cited

YearCitations
20231
202410
20257
20266

Top states: CO (3), TN (3), HI (3), TX (3), MA (2)

Largest penalties

EmployerLocationPenalty for this rule
DACON CORPORATIONLA PORTE, TX$16,550
ALLIED POWER SERVICES, LLCCLINTON, IL$16,550
JERSEY CENTRAL POWER & LIGHT COMPANYSAYREVILLE, NJ$16,000
RIO GRANDE ELECTRIC COOPERATIVE, INC.MARATHON, TX$14,895
DUQUESNE LIGHT COMPANYPITTSBURGH, PA$14,471

Free toolbox talk

A 5-minute crew talk on 1910.269(m), plus alerts when this rule changes. Free.




OSHA interpretation letters

Related parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey, Dana Reyes

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

Who is in charge of the clearance?

One employee in the crew designated by the employer.

How are lines deenergized under other procedures treated?

As energized.

When can some steps and tags be skipped?

When only one crew is working and the disconnect is accessible, visible and under the sole control of the employee in charge; (m)(3)(i), (iii) and (v) and tags do not apply.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.