29 CFR 1926.1400(c) ("Exclusions") is one requirement inside 1926.1400 Scope, an OSHA construction standard (Part 1926, Subpart CC). It includes 25 sub-paragraphs. The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.
Official text
(c) Exclusions. This subpart does not cover:
(1) Machinery included in paragraph (a) of this section while it has been converted or adapted for a non-hoisting/lifting use. Such conversions/adaptations include, but are not limited to, power shovels, excavators and concrete pumps.
(2) Power shovels, excavators, wheel loaders, backhoes, loader backhoes, track loaders. This machinery is also excluded when used with chains, slings or other rigging to lift suspended loads.
(3) Automotive wreckers and tow trucks when used to clear wrecks and haul vehicles.
(4) Digger derricks when used for augering holes for poles carrying electric or telecommunication lines, placing and removing the poles, and for handling associated materials for installation on, or removal from, the poles, or when used for any other work subject to subpart V of this part. To be eligible for this exclusion, digger-derrick use in work subject to subpart V of this part must comply with all of the provisions of that subpart, and digger-derrick use in construction work for telecommunication service (as defined at § 1910.268(s)(40)) must comply with all of the provisions of § 1910.268.
(5) Machinery originally designed as vehicle-mounted aerial devices (for lifting personnel) and self-propelled elevating work platforms.
(6) Telescopic/hydraulic gantry systems.
(7) Stacker cranes.
(8) Powered industrial trucks (forklifts), except when configured to hoist and lower (by means of a winch or hook) and horizontally move a suspended load.
(9) Mechanic's truck with a hoisting device when used in activities related to equipment maintenance and repair.
(10) Machinery that hoists by using a come-a-long or chainfall.
(11) Dedicated drilling rigs.
(12) Gin poles when used for the erection of communication towers.
(13) Tree trimming and tree removal work.
(14) Anchor handling or dredge-related operations with a vessel or barge using an affixed A-frame. Open (c)(14)
(15) Roustabouts.
(16) Helicopter cranes.
(17) Material delivery. Open (c)(17)
(i) Articulating/knuckle-boom truck cranes that deliver material to a construction site when used to transfer materials from the truck crane to the ground, without arranging the materials in a particular sequence for hoisting. Open (c)(17)(i)
(ii) Articulating/knuckle-boom truck cranes that deliver material to a construction site when the crane is used to transfer building supply sheet goods or building supply packaged materials from the truck crane onto a structure, using a fork/cradle at the end of the boom, but only when the truck crane is equipped with a properly functioning automatic overload prevention device. Such sheet goods or packaged materials include, but are not limited to: Sheets of sheet rock, sheets of plywood, bags of cement, sheets or packages of roofing shingles, and rolls of roofing felt.
(iii) This exclusion does not apply when:
(A) The articulating/knuckle-boom crane is used to hold, support or stabilize the material to facilitate a construction activity, such as holding material in place while it is attached to the structure;
(B) The material being handled by the articulating/knuckle-boom crane is a prefabricated component. Such prefabricated components include, but are not limited to: Precast concrete members or panels, roof trusses (wooden, cold-formed metal, steel, or other material), prefabricated building sections such as, but not limited to: Floor panels, wall panels, roof panels, roof structures, or similar items;
(C) The material being handled by the crane is a structural steel member (for example, steel joists, beams, columns, steel decking (bundled or unbundled) or a component of a systems-engineered metal building (as defined in 29 CFR 1926 subpart R).
(D) The activity is not specifically excluded under § 1400(c)(17)(i) and (ii).
(18) Flash-butt welding trucks. Flash-butt welding trucks or other roadway maintenance machines not equipped with any hoisting device other than that used to suspend and move a welding device or workhead assembly. For purposes of this paragraph (c)(18), the terms flash-butt welding truck and roadway maintenance machine refer to railroad equipment that meets the definition of “roadway maintenance machine” in 49 CFR 214.7 and is used only for railroad track work.
Source: eCFR, text current as of 2026-10-15. Read all of 1926.1400.
Free toolbox talk
A 5-minute crew talk on 1926.1400(c), plus alerts when this rule changes. Free.
OSHA interpretation letters
- Application of construction crane standard when handling precast components (2016-07-28)
- Clarification of whether the handling of propane tanks is considered construction (2016-06-27)
- Whether unloading a pallet suspended by a crane is considered construction. (2016-06-23)
- Applicability of Supbart CC standards to equipment with dragline attachments. (2012-10-03)
Related parts of this rule
Get your crew competent
Trainers on Black Belt Safety: Marc Harvey, Dana Reyes
Trainers and suppliers: feature your business on this rule for $25/month.
About this page
Sources
- 29 CFR 1926.1400 (eCFR), text current as of 2026-10-15