29 CFR 1910.106(b)(7) ("Testing") is one requirement inside 1910.106 Flammable liquids, an OSHA general industry standard (Part 1910, Subpart H). It includes 5 sub-paragraphs. The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.
Official text
(7) Testing — 2 citations
(i) General. All tanks, whether shop built or field erected, shall be strength tested before they are placed in service in accordance with the applicable paragraphs of the code under which they were built. The American Society of Mechanical Engineers (ASME) code stamp, American Petroleum Institute (API) monogram, or the label of the Underwriters' Laboratories, Inc., on a tank shall be evidence of compliance with this strength test. Tanks not marked in accordance with the above codes shall be strength tested before they are placed in service in accordance with good engineering principles and reference shall be made to the sections on testing in the codes listed in subparagraphs (1) (iii)(a), (iv)(b), or (v)(b) of this paragraph. 2 citations
(ii) Strength. When the vertical length of the fill and vent pipes is such that when filled with liquid the static head imposed upon the bottom of the tank exceeds 10 pounds per square inch, the tank and related piping shall be tested hydrostatically to a pressure equal to the static head thus imposed.
(iii) Tightness. In addition to the strength test called for in subdivisions (i) and (ii) of this subparagraph, all tanks and connections shall be tested for tightness. Except for underground tanks, this tightness test shall be made at operating pressure with air, inert gas, or water prior to placing the tank in service. In the case of field-erected tanks the strength test may be considered to be the test for tank tightness. Underground tanks and piping, before being covered, enclosed, or placed in use, shall be tested for tightness hydrostatically, or with air pressure at not less than 3 pounds per square inch and not more than 5 pounds per square inch.
(iv) Repairs. All leaks or deformations shall be corrected in an acceptable manner before the tank is placed in service. Mechanical caulking is not permitted for correcting leaks in welded tanks except pinhole leaks in the roof.
(v) Derated operations. Tanks to be operated at pressures below their design pressure may be tested by the applicable provisions of subdivision (i) or (ii) of this subparagraph, based upon the pressure developed under full emergency venting of the tank.
Source: eCFR, text current as of 2026-10-15. Read all of 1910.106.
Where and how often it was cited
Free toolbox talk
A 5-minute crew talk on 1910.106(b)(7), plus alerts when this rule changes. Free.
OSHA interpretation letters
- Testing requirements for piping, valves, and fittings; Testing requirements for piping, valves, and fittings (1983-11-14)
Related parts of this rule
- 1910.106(b) Tank storage 99 citations
- 1910.106(b)(6) Sources of ignition 59 citations
- 1910.106(b)(2) Installation of outside aboveground tanks 23 citations
- 1910.106(b)(2)(vii) Drainage, dikes, and walls for aboveground tanks— 13 citations
- 1910.106(b)(4) Installation of tanks inside of buildings 6 citations
- 1910.106(b)(2)(ii) Spacing (shell-to-shell) between aboveground tanks 5 citations
- 1910.106(b)(5) Supports, foundations, and anchorage for all tank locations 5 citations
- 1910.106(b)(1) Design and construction of tanks 4 citations
- 1910.106(b)(4)(ii) Vents 2 citations
- 1910.106(b)(4)(iv) Tank openings other than vents 2 citations
- 1910.106(b)(1)(i) Materials 1 citations
- 1910.106(b)(5)(ii) Fire resistance
Get your crew competent
Trainers on Black Belt Safety: Marc Harvey, Dana Reyes
Trainers and suppliers: feature your business on this rule for $25/month.
About this page
Sources
- 29 CFR 1910.106 (eCFR), text current as of 2026-10-15
- U.S. Department of Labor enforcement data: OSHA inspections, citations and accident records, copied nightly; data as of 2026-10-21
3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.