29 CFR 1926 · Construction · Subpart Z

1926.1101(g)(8): Extra Controls for Class II Asbestos Work

By Black Belt Safety Editorial Team Official text as of October 15, 2026 Data updated October 20, 2026 9 min read

In plain words:

Employers must perform Class II asbestos work using the work practices and controls set for each type of job, and may choose one or a combination of the listed methods. For vinyl and asphalt flooring with ACM, or not verified ACM-free in buildings built no later than 1980, workers must be trained and must not sand flooring, dry sweep or rip up resilient sheeting.

Key takeaways

  • 1926.1101(g)(8) is part of OSHA's construction standards (29 CFR Part 1926, Subpart Z).
  • OSHA cited it 71 times in the last 3 years, in 44 inspections, with $118,173 in current penalties.
  • Most citations: VA (19), MA (8), NC (7).
  • Related part: 1926.1101(g) Methods of compliance (297 citations).
  • Free 5-minute toolbox talk for your crew below.
71citations, 3 years
$118,173current penalties
44inspections
0linked injury cases
In this article
  1. What this rule covers
  2. Official text
  3. Where and how often it was cited
  4. Free toolbox talk
  5. OSHA interpretation letters
  6. Related parts of this rule
  7. Get your crew competent
  8. Frequently asked questions
  9. About this page

What this rule covers

29 CFR 1926.1101(g)(8) ("Additional Controls for Class II work") is one requirement inside 1926.1101 Asbestos, an OSHA construction standard (Part 1926, Subpart Z). It includes 37 sub-paragraphs. The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

(8) Additional Controls for Class II work. Class II asbestos work shall also be performed by complying with the work practices and controls designated for each type of asbestos work to be performed, set out in this paragraph. Where more than one control method may be used for a type of asbestos work, the employer may choose one or a combination of designated control methods. Class II work also may be performed using a method allowed for Class I work, except that glove bags and glove boxes are allowed if they fully enclose the Class II material to be removed. 71 citations

(i) For removing vinyl and asphalt flooring materials which contain ACM or for which in buildings constructed no later than 1980, the employer has not verified the absence of ACM pursuant to paragraph (g)(8)(i)(I) of this section. The employer shall ensure that employees comply with the following work practices and that employees are trained in these practices pursuant to paragraph (k)(9): Open (g)(8)(i) 28 citations

(A) Flooring or its backing shall not be sanded. 1 citations

(B) Vacuums equipped with HEPA filter, disposable dust bag, and metal floor tool (no brush) shall be used to clean floors. 1 citations

(C) Resilient sheeting shall be removed by cutting with wetting of the snip point and wetting during delamination. Rip-up of resilient sheet floor material is prohibited.

(D) All scraping of residual adhesive and/or backing shall be performed using wet methods. Open (g)(8)(i)(d) 2 citations

(E) Dry sweeping is prohibited. 2 citations

(F) Mechanical chipping is prohibited unless performed in a negative pressure enclosure which meets the requirements of paragraph (g)(5)(i) of this section. 3 citations

(G) Tiles shall be removed intact, unless the employer demonstrates that intact removal is not possible. 4 citations

(H) When tiles are heated and can be removed intact, wetting may be omitted.

(I) Resilient flooring material including associated mastic and backing shall be assumed to be asbestos-containing unless an industrial hygienist determines that it is asbestos-free using recognized analytical techniques. 4 citations

(ii) For removing roofing material which contains ACM the employer shall ensure that the following work practices are followed: Open (g)(8)(ii) 18 citations

(A) Roofing material shall be removed in an intact state to the extent feasible. 1 citations

(B) Wet methods shall be used to remove roofing materials that are not intact, or that will be rendered not intact during removal, unless such wet methods are not feasible or will create safety hazards. 4 citations

(C) Cutting machines shall be continuously misted during use, unless a competent person determines that misting substantially decreases worker safety.

(D) When removing built-up roofs with asbestos-containing roofing felts and an aggregate surface using a power roof cutter, all dust resulting from the cutting operation shall be collected by a HEPA dust collector, or shall be HEPA vacuumed by vacuuming along the cut line. When removing built-up roofs with asbestos-containing roofing felts and a smooth surface using a power roof cutter, the dust resulting from the cutting operation shall be collected either by a HEPA dust collector or HEPA vacuuming along the cut line, or by gently sweeping and then carefully and completely wiping up the still-wet dust and debris left along the cut line. The dust and debris shall be immediately bagged or placed in covered containers.

(E) Asbestos-containing material that has been removed from a roof shall not be dropped or thrown to the ground. Unless the material is carried or passed to the ground by hand, it shall be lowered to the ground via covered, dust-tight chute, crane or hoist: 8 citations

(1) Any ACM that is not intact shall be lowered to the ground as soon as is practicable, but in any event no later than the end of the work shift. While the material remains on the roof it shall either be kept wet, placed in an impermeable waste bag, or wrapped in plastic sheeting.

(2) Intact ACM shall be lowered to the ground as soon as is practicable, but in any event no later than the end of the work shift.

(F) Upon being lowered, unwrapped material shall be transferred to a closed receptacle in such manner so as to preclude the dispersion of dust. 4 citations

(G) Roof level heating and ventilation air intake sources shall be isolated or the ventilation system shall be shut down.

(H) Notwithstanding any other provision of this section, removal or repair of sections of intact roofing less than 25 square feet in area does not require use of wet methods or HEPA vacuuming as long as manual methods which do not render the material non-intact are used to remove the material and no visible dust is created by the removal method used. In determining whether a job involves less than 25 square feet, the employer shall include all removal and repair work performed on the same roof on the same day.

(iii) When removing cementitious asbestos-containing siding and shingles or transite panels containing ACM on building exteriors (other than roofs, where paragraph (g)(8)(ii) of this section applies) the employer shall ensure that the following work practices are followed: Open (g)(8)(iii) 15 citations

(A) Cutting, abrading or breaking siding, shingles, or transite panels, shall be prohibited unless the employer can demonstrate that methods less likely to result in asbestos fiber release cannot be used. 6 citations

(B) Each panel or shingle shall be sprayed with amended water prior to removal. 3 citations

(C) Unwrapped or unbagged panels or shingles shall be immediately lowered to the ground via covered dust-tight chute, crane or hoist, or placed in an impervious waste bag or wrapped in plastic sheeting and lowered to the ground no later than the end of the work shift. 3 citations

(D) Nails shall be cut with flat, sharp instruments. 1 citations

(iv) When removing gaskets containing ACM, the employer shall ensure that the following work practices are followed: Open (g)(8)(iv)

(A) If a gasket is visibly deteriorated and unlikely to be removed intact, removal shall be undertaken within a glovebag as described in paragraph (g)(5)(ii) of this section. Open (g)(8)(iv)(a)

(B) [Reserved]

(C) The gasket shall be immediately placed in a disposal container.

(D) Any scraping to remove residue must be performed wet.

(v) When performing any other Class II removal of asbestos containing material for which specific controls have not been listed in paragraph (g)(8)(i) through (iv) of this section, the employer shall ensure that the following work practices are complied with. 9 citations

(A) The material shall be thoroughly wetted with amended water prior to and during its removal. 3 citations

(B) The material shall be removed in an intact state unless the employer demonstrates that intact removal is not possible. 1 citations

(C) Cutting, abrading or breaking the material shall be prohibited unless the employer can demonstrate that methods less likely to result in asbestos fiber release are not feasible. 3 citations

(D) Asbestos-containing material removed, shall be immediately bagged or wrapped, or kept wetted until transferred to a closed receptacle, no later than the end of the work shift. 2 citations

(vi) Alternative Work Practices and Controls. Instead of the work practices and controls listed in paragraph (g)(8) (i) through (v) of this section, the employer may use different or modified engineering and work practice controls if the following provisions are complied with. Open (g)(8)(vi)

(A) The employer shall demonstrate by data representing employee exposure during the use of such method under conditions which closely resemble the conditions under which the method is to be used, that employee exposure will not exceed the PELs under any anticipated circumstances.

(B) A competent person shall evaluate the work area, the projected work practices and the engineering controls, and shall certify in writing, that the different or modified controls are adequate to reduce direct and indirect employee exposure to below the PELs under all expected conditions of use and that the method meets the requirements of this standard. The evaluation shall include and be based on data representing employee exposure during the use of such method under conditions which closely resemble the conditions under which the method is to be used for the current job, and by employees whose training and experience are equivalent to employees who are to perform the current job.

Source: eCFR, text current as of 2026-10-15. Read all of 1926.1101.

Where and how often it was cited

YearCitations
20233
202426
202528
202614

Top states: VA (19), MA (8), NC (7), OR (6), IL (4)

Largest penalties

EmployerLocationPenalty for this rule
ACCOLADE ENVIRONMENTAL CONTRACTING, CORP.BOSTON, MA$33,103
ARSI ASBESTOS REMOVAL SERVICES INC.MOBERLY, MO$16,134
FINCHUM SPORTS FLOORS L.L.C.ABINGDON, VA$11,905
317741862 - ROSE CITY CONTRACTING INCPORTLAND, OR$8,474
JM ROMICH ENTERPRISES, INCGREECE, NY$5,250

Free toolbox talk

A 5-minute crew talk on 1926.1101(g)(8), plus alerts when this rule changes. Free.




OSHA interpretation letters

Related parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey, Dana Reyes

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

Can asbestos floor tile be sanded?

No. For covered vinyl and asphalt flooring, flooring or its backing shall not be sanded.

What vacuum must be used to clean floors?

Vacuums equipped with a HEPA filter, disposable dust bag and metal floor tool with no brush.

Can Class I methods be used for Class II work?

Yes, except that glove bags and glove boxes are allowed only if they fully enclose the Class II material being removed.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.