29 CFR 1926 · Construction · Subpart Q

1926.703(b): Shoring and Reshoring for Concrete

By Black Belt Safety Editorial Team Official text as of October 15, 2026 Data updated October 19, 2026 4 min read

In plain words:

Employers must inspect shoring equipment before erection to confirm it meets the formwork drawings, not use damaged shoring, and inspect erected shoring immediately before, during and immediately after concrete placement. Damaged shoring found after erection must be reinforced immediately, sills must be sound, parts must be in firm contact, and tiered single post shores need a qualified design, engineer inspection, alignment, splicing and bracing.

Key takeaways

  • 1926.703(b) is part of OSHA's construction standards (29 CFR Part 1926, Subpart Q).
  • OSHA cited it 16 times in the last 3 years, in 12 inspections, with $74,817 in current penalties.
  • Most citations: FL (6), CT (3), DE (3).
  • Related part: 1926.703(b)(8) (3 citations).
  • Free 5-minute toolbox talk for your crew below.
16citations, 3 years
$74,817current penalties
12inspections
0linked injury cases
In this article
  1. What this rule covers
  2. Official text
  3. Where and how often it was cited
  4. Free toolbox talk
  5. OSHA interpretation letters
  6. Related parts of this rule
  7. Get your crew competent
  8. Frequently asked questions
  9. About this page

What this rule covers

29 CFR 1926.703(b) ("Shoring and reshoring") is one requirement inside 1926.703 Requirements for cast-in-place concrete, an OSHA construction standard (Part 1926, Subpart Q). It includes 14 sub-paragraphs. The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

(b) Shoring and reshoring. 16 citations

(1) All shoring equipment (including equipment used in reshoring operations) shall be inspected prior to erection to determine that the equipment meets the requirements specified in the formwork drawings. 1 citations

(2) Shoring equipment found to be damaged such that its strength is reduced to less than that required by § 1926.703(a)(1) shall not be used for shoring.

(3) Erected shoring equipment shall be inspected immediately prior to, during, and immediately after concrete placement. 3 citations

(4) Shoring equipment that is found to be damaged or weakened after erection, such that its strength is reduced to less than that required by § 1926.703(a)(1), shall be immediately reinforced.

(5) The sills for shoring shall be sound, rigid, and capable of carrying the maximum intended load.

(6) All base plates, shore heads, extension devices, and adjustment screws shall be in firm contact, and secured when necessary, with the foundation and the form. 9 citations

(7) Eccentric loads on shore heads and similar members shall be prohibited unless these members have been designed for such loading.

(8) Whenever single post shores are used one on top of another (tiered), the employer shall comply with the following specific requirements in addition to the general requirements for formwork: Open (b)(8) 3 citations

(i) The design of the shoring shall be prepared by a qualified designer and the erected shoring shall be inspected by an engineer qualified in structural design. Open (b)(8)(i) 2 citations

(ii) The single post shores shall be vertically aligned.

(iii) The single post shores shall be spliced to prevent misalignment.

(iv) The single post shores shall be adequately braced in two mutually perpendicular directions at the splice level. Each tier shall also be diagonally braced in the same two directions. 1 citations

(9) Adjustment of single post shores to raise formwork shall not be made after the placement of concrete.

(10) Reshoring shall be erected, as the original forms and shores are removed, whenever the concrete is required to support loads in excess of its capacity.

Source: eCFR, text current as of 2026-10-15. Read all of 1926.703.

Where and how often it was cited

YearCitations
20233
20247
20251
20265

Top states: FL (6), CT (3), DE (3), NY (2), TX (1)

Largest penalties

EmployerLocationPenalty for this rule
KMI, INC.BROOKLYN, NY$33,100
SEVEN CONCRETE, LLCNEW HAVEN, CT$18,000
TAS COMMERCIAL CONCRETE CONSTRUCTION, LPHOUSTON, TX$6,098
K N M CONSTRUCTIONS CORPHIALEAH, FL$5,740
JKJ CONCRETE, INC.WILMINGTON, DE$4,610

Free toolbox talk

A 5-minute crew talk on 1926.703(b), plus alerts when this rule changes. Free.




OSHA interpretation letters

Related parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey, Dana Reyes

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

When must erected shoring be inspected?

Immediately prior to, during, and immediately after concrete placement.

Can damaged shoring be used?

Not if the damage reduces its strength below what 1926.703(a)(1) requires.

Who must design tiered single post shores?

A qualified designer, and the erected shoring must be inspected by an engineer qualified in structural design.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.

Scroll to top