In plain words:

In steel erection, the crane rules in subpart CC apply to hoisting and rigging, except 1926.1431(a). Cranes used in steel erection must be visually inspected before each shift by a competent person, checking controls, safety devices, lines, hooks and latches, wire rope reeving, electrical parts, hydraulics, tires, ground conditions and level position. If a deficiency is found, the competent person must immediately determine whether it is a hazard.

Key takeaways

  • 1926.753 is part of OSHA's construction standards (29 CFR Part 1926, Subpart R).
  • OSHA cited it 27 times in the last 3 years, in 22 inspections, with $136,335 in current penalties.
  • Most citations: TX (6), MA (4), NC (4).
  • Most-cited part: 1926.753(d) Working under loads (17 citations).
  • Free 5-minute toolbox talk for your crew below.

Get the free 5-minute toolbox talk on 1926.753 ↓

27citations, 3 years
$136,335current penalties
22inspections
0linked injury cases
In this article
  1. What this rule covers
  2. Official text
  3. Where and how often it was cited
  4. Free toolbox talk
  5. OSHA interpretation letters
  6. Most-cited parts of this rule
  7. Get your crew competent
  8. Frequently asked questions
  9. About this page

What this rule covers

29 CFR 1926.753, "Hoisting and rigging", is an OSHA construction standard (Part 1926, Subpart R). It has 51 numbered paragraphs. The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

Show the full text of 1926.753 (51 paragraphs)

(a) All the provisions of subpart CC apply to hoisting and rigging with the exception of § 1926.1431(a).

(b) In addition, paragraphs (c) through (e) of this section apply regarding the hazards associated with hoisting and rigging.

(c) General. Open (c) 10 citations

(1) Pre-shift visual inspection of cranes. Open (c)(1) 3 citations

(i) Cranes being used in steel erection activities shall be visually inspected prior to each shift by a competent person; the inspection shall include observation for deficiencies during operation. At a minimum this inspection shall include the following: Open (c)(1)(i) 2 citations

(A) All control mechanisms for maladjustments;

(B) Control and drive mechanism for excessive wear of components and contamination by lubricants, water or other foreign matter;

(C) Safety devices, including but not limited to boom angle indicators, boom stops, boom kick out devices, anti-two block devices, and load moment indicators where required;

(D) Air, hydraulic, and other pressurized lines for deterioration or leakage, particularly those which flex in normal operation;

(E) Hooks and latches for deformation, chemical damage, cracks, or wear;

(F) Wire rope reeving for compliance with hoisting equipment manufacturer's specifications;

(G) Electrical apparatus for malfunctioning, signs of excessive deterioration, dirt, or moisture accumulation;

(H) Hydraulic system for proper fluid level;

(I) Tires for proper inflation and condition;

(J) Ground conditions around the hoisting equipment for proper support, including ground settling under and around outriggers, ground water accumulation, or similar conditions;

(K) The hoisting equipment for level position; and

(L) The hoisting equipment for level position after each move and setup. 1 citations

(ii) If any deficiency is identified, an immediate determination shall be made by the competent person as to whether the deficiency constitutes a hazard.

(iii) If the deficiency is determined to constitute a hazard, the hoisting equipment shall be removed from service until the deficiency has been corrected.

(iv) The operator shall be responsible for those operations under the operator's direct control. Whenever there is any doubt as to safety, the operator shall have the authority to stop and refuse to handle loads until safety has been assured. 1 citations

(2) A qualified rigger (a rigger who is also a qualified person) shall inspect the rigging prior to each shift in accordance with § 1926.251. Open (c)(2) 7 citations

(3) The headache ball, hook or load shall not be used to transport personnel except as provided in paragraph (c)(4) of this section.

(4) Cranes or derricks may be used to hoist employees on a personnel platform when work under this subpart is being conducted, provided that all provisions of § 1926.1431 (except for § 1926.1431(a)) are met.

(5) Safety latches on hooks shall not be deactivated or made inoperable except: Open (c)(5)

(i) When a qualified rigger has determined that the hoisting and placing of purlins and single joists can be performed more safely by doing so; or

(ii) When equivalent protection is provided in a site-specific erection plan.

(d) Working under loads. Open (d) 17 citations

(1) Routes for suspended loads shall be pre-planned to ensure that no employee is required to work directly below a suspended load except for: 2 citations

(i) Employees engaged in the initial connection of the steel; or

(ii) Employees necessary for the hooking or unhooking of the load.

(2) When working under suspended loads, the following criteria shall be met: Open (d)(2) 15 citations

(i) Materials being hoisted shall be rigged to prevent unintentional displacement; 4 citations

(ii) Hooks with self-closing safety latches or their equivalent shall be used to prevent components from slipping out of the hook; and 3 citations

(iii) All loads shall be rigged by a qualified rigger 7 citations

(e) Multiple lift rigging procedure. Open (e)

(1) A multiple lift shall only be performed if the following criteria are met:

(i) A multiple lift rigging assembly is used;

(ii) A maximum of five members are hoisted per lift;

(iii) Only beams and similar structural members are lifted; and

(iv) All employees engaged in the multiple lift have been trained in these procedures in accordance with § 1926.761(c)(1).

(v) No crane is permitted to be used for a multiple lift where such use is contrary to the manufacturer's specifications and limitations.

(2) Components of the multiple lift rigging assembly shall be specifically designed and assembled with a maximum capacity for total assembly and for each individual attachment point. This capacity, certified by the manufacturer or a qualified rigger, shall be based on the manufacturer's specifications with a 5 to 1 safety factor for all components.

(3) The total load shall not exceed:

(i) The rated capacity of the hoisting equipment specified in the hoisting equipment load charts;

(ii) The rigging capacity specified in the rigging rating chart.

(4) The multiple lift rigging assembly shall be rigged with members:

(i) Attached at their center of gravity and maintained reasonably level;

(ii) Rigged from top down; and

(iii) Rigged at least 7 feet (2.1 m) apart.

(5) The members on the multiple lift rigging assembly shall be set from the bottom up.

(6) Controlled load lowering shall be used whenever the load is over the connectors.

[66 FR 5265, Jan. 18, 2001, as amended at 75 FR 48134, Aug. 9, 2010]

Source: eCFR, text current as of 2026-10-15.

See every company cited for this rule.

Export the list: 22 inspections cited 1926.753 in the last 3 years, with employer, location, penalty and date.

Purple Belt, $59/mo

Where and how often it was cited

YearCitations
20232
20245
202511
20269

Top states: TX (6), MA (4), NC (4), FL (3), KY (2)

Largest penalties

EmployerLocationPenalty for this rule
159485 - ZA CONSTRUCTION OF MS, LLCGREEN MOUNTAIN, NC$33,100
FLINTCO, LLCHOUSTON, TX$16,550
HME, INC.PERRY, KS$13,240
LFC MANAGEMENT SERVICES, INC.NAPLES, FL$11,585
CONTRAST METALWORKS LLCPHILADELPHIA, PA$10,938

Free toolbox talk

A 5-minute crew talk on 1926.753, plus alerts when this rule changes. Free.




OSHA interpretation letters

None exist. OSHA has not published a letter of interpretation for 1926.753.

Most-cited parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

Who inspects cranes before each shift?

A competent person, including observation for deficiencies during operation.

What does the pre-shift inspection cover?

Items including controls, safety devices, pressurized lines, hooks and latches, wire rope reeving, electrical apparatus, hydraulic fluid, tires, ground conditions and level position.

What happens if a deficiency is found?

The competent person must make an immediate determination of whether it is a hazard.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.

Scroll to top