1926.451(f)(6): Scaffold Clearance From Power Lines

By Black Belt Safety Editorial Team Official text as of October 15, 2026 Data updated October 19, 2026 3 min read

In plain words:

Employers must not erect, use, dismantle, alter or move scaffolds so that the scaffold or conductive material on it comes closer to energized power lines than the rule's table allows, such as 3 feet for insulated lines under 300 volts and 10 feet for uninsulated lines under 50 kv. Closer work is allowed only after the utility or system operator is notified and deenergizes, relocates or covers the lines.

Key takeaways

  • 1926.451(f)(6) is part of OSHA's construction standards (29 CFR Part 1926, Subpart L).
  • OSHA cited it 108 times in the last 3 years, in 108 inspections, with $377,374 in current penalties.
  • 3 deaths are linked to inspections that cited this rule.
  • Most citations: NJ (27), MA (23), IL (11).
  • Related part: 1926.451(f) Use (1,223 citations).
  • Free 5-minute toolbox talk for your crew below.
108citations, 3 years
$377,374current penalties
108inspections
3linked deaths
In this article
  1. What this rule covers
  2. Official text
  3. Injuries linked to this rule
  4. Where and how often it was cited
  5. Free toolbox talk
  6. OSHA interpretation letters
  7. Related parts of this rule
  8. Get your crew competent
  9. Frequently asked questions
  10. About this page

What this rule covers

29 CFR 1926.451(f)(6) is one requirement inside 1926.451 General requirements, an OSHA construction standard (Part 1926, Subpart L). The official text below is copied word for word from the Electronic Code of Federal Regulations (eCFR). The numbers, injury cases and training on this page show how OSHA enforces it on real job sites.

Official text

(6) The clearance between scaffolds and power lines shall be as follows: Scaffolds shall not be erected, used, dismantled, altered, or moved such that they or any conductive material handled on them might come closer to exposed and energized power lines than as follows: 108 citations

Insulated lines
voltage
Minimum distance Alternatives
Less than 300 volts 3 feet (0.9 m)
300 volts to 50 kv 10 feet (3.1m)
More than 50 kv 10 feet (3.1 m) plus 0.4 inches (1.0 cm) for each 1 kv over 50 kv 2 times the length of the line insulator, but never less than 10 feet (3.1 m).
Uninsulated lines
voltage
Minimum distance Alternatives
Less than 50 kv 10 feet (3.1 m)
More than 50 kv 10 feet (3.1 m) plus 0.4 inches (1.0 cm) for each 1 kv over 50 kv 2 times the length of the line insulator, but never less than 10 feet (3.1 m).

Scaffolds and materials may be closer to power lines than specified above where such clearance is necessary for performance of work, and only after the utility company, or electrical system operator, has been notified of the need to work closer and the utility company, or electrical system operator, has deenergized the lines, relocated the lines, or installed protective coverings to prevent accidental contact with the lines.

Source: eCFR, text current as of 2026-10-15. Read all of 1926.451.

Injuries linked to this rule

3 deaths are linked to inspections where OSHA cited 1926.451(f)(6).

Employee electrocuted removing gutter
2025-03-04 · Fatal · FALL RIVER, MA

Employee was removing a gutter from a residential structure working from a pump-jack scaffold system erected 4.5 feet from a 79 kilovolt primary power line. The gutter contacted the power line and the employee was electrocuted.

See all 3 cases

Full case list with employer, penalty, filters and download is part of OSHA Data (Purple Belt).

Unlock with Purple Belt

Where and how often it was cited

YearCitations
20237
202437
202544
202620

Top states: NJ (27), MA (23), IL (11), NY (9), PA (9)

Largest penalties

EmployerLocationPenalty for this rule
DRORE 2, LLCFORT LAUDERDALE, FL$27,000
A-CLASS CONSTRUCTION CORPORATIONPHILADELPHIA, PA$16,550
ARCO/MURRAY NATIONAL DALLAS, INC.ENGLEWOOD, NJ$16,131
NEW ENTERPRISE STONE & LIME COMPANY, INC.HARRISBURG, PA$15,000
ELITE BROTHERS CONSTRUCTION LLCNEWARK, NJ$11,916

Free toolbox talk

A 5-minute crew talk on 1926.451(f)(6), plus alerts when this rule changes. Free.




OSHA interpretation letters

Related parts of this rule

Get your crew competent

Trainers on Black Belt Safety: Marc Harvey, Dana Reyes

Trainers and suppliers: feature your business on this rule for $25/month.

Frequently asked questions

How close can a scaffold be to an uninsulated line under 50 kv?

No closer than 10 feet (3.1 m).

What about insulated lines under 300 volts?

The minimum distance is 3 feet (0.9 m).

Can a scaffold ever be closer than the table allows?

Only when necessary for the work, and only after the utility or electrical system operator has been notified and has deenergized, relocated or covered the lines.

About this page

Sources

3-year window. Federal OSHA only; state-plan rules are not counted. Plain-language text is a summary, not legal advice; the official text controls. Black Belt Safety is not part of OSHA or the Department of Labor.

Written and reviewed by

Black Belt Safety Editorial Team

Site Safety Officer and Safety Professional

OSHA 30 · CPR · USACE CQM

Written and reviewed by the Black Belt Safety team. Every post is checked against the OSHA standard or agency source it cites.